Saturday, 8 December 2012

Not long to go now

There is 5 days until our apparent handover date.

Our PCI walk through was pushed back from last Wednesday afternoon to tomorrow afternoon.

The list I posted last week still has a lot outstanding which concerns me.

The things that got completed from the list were insulation was spread in the roof, the tiler completed the tiling upstairs, but still needs to return to finish the splashback and the inside was cleaned up a bit.

Which leaves 5 days for the following things to be done.... as well as a few defects we've picked up along the way.

- shower screens, wardrobe railings, shelving in pantry, mirrors
- fly screens and screen doors
- acid burnt bricks need replacing & a few bricks need fixing.
- inspection point needs to be bricked up
- timber screen to the front facade needs to be installed (enter worlds slowest carpenter again!)
- paint touch ups
- carpet
- tiling - kitchen splashback
- stair case needs to be stained
- site clean up
- internal clean (final clean)

Carpet is meant to be tomorrow, staircase was meant to be painted on Saturday, which didn't happen.
Our SS queried our stain colour, which has made me nervous. We had chosen Ebony as per the display home, but our SS said it's very dark, so a few frantic phone calls to the lovely interior ladies and I am hoping it turns out okay.

We NEED to handover on Friday as we have to hand back our rental keys on the Tuesday afternoon.

In other news, one of our lounges has been delivered, it is still in boxes, can't wait to open it!!
Our rental resembles a warehouse with boxes everywhere. The clutter is making me twitchy.

The DA for the retaining wall was approved last week. So will be ready to start that as soon as we're in.

Good news, the bank valuation has come through and I can pick up the final cheque on Friday morning, I am so glad that is all sorted, I was petrified that the bank would delay things.

Fingers crossed everything falls into place this week, I can't wait to move into my beautiful new home, and unpack all our belongings that have been boxed up for over a year now.

Better keep packing, there is still a bit to box up & a whole lot of cleaning to do!










Thursday, 29 November 2012

Countdown is on!

2 weeks until handover...

Assuming all goes to plan.

I am quietly confident that everything will come together nicely, but I don't want to get my hopes up too high.

We have handed in our notice to our real estate agent, paid for our insurance and we received our final progress payment yesterday and that has been sent off to the bank.
Let's hope the bank gets its act together and processes it quickly and doesn't delay anything.

We had a sticky beak in the window yesterday, the tiler has been there tiling the main living area floor downstairs. It looks fantastic.

We have a walk through booked in for next Wednesday, so hopefully all the little things that need doing will be done or close to being done.

A few things left to do still;
- shower screens, wardrobe railings, shelving in pantry, mirrors
- fly screens and screen doors
- insulation in the roof requires spreading
- acid burnt bricks need replacing & a few bricks need fixing.
- timber screen to the front facade needs to be installed
- paint touch ups
- carpet
- tiling - a couple of tiles need to be done
- stair case needs to be stained
- site clean up
- internal clean

And then the obvious ones, all the installation of appliances etc on handover.

We are taking delivery of one of our lounges next Wednesday, not sure where we'll store that, but King couldn't deliver it once we were in because their warehouse is under renovation.

The DA for retaining walls should be through soon, we had to submit additional paperwork, so now we just wait!
That's our Christmas job, installed 900mm high retaining walls to the rear of our block and to the sides.



Tuesday, 20 November 2012

A walk through...

We had the opportunity to walk through the house today. I finally got to meet our lovely supervisor.
My husband has been meeting with our supervisor regularly and this is the first time I have been able to attend.

Handover is still looking like the 14th December.
Everything is booked in and going to plan.

Very happy with our colours, selections and most importantly extremely happy with our builder.
Our supervisor has worked hard to ensure everything is completed to the highest standard and has a fantastic eye for detail and picked up things we never would have seen.

Now to get all our paperwork sorted for the final payment. Last time we put through a payment the bank was painfully slow and took 3 weeks for them to send a valuer out to approve the payment.

Here are some photos;

Bedroom 2 - Martini Paint


Towel Rail - Main Bathroom


Main Bathroom


Looking from the front door


Feature Wall - Taubmans Stone Drab
 
Feature Wall - Taubmans Stone Drab


Upstairs Powder Room
 


 



Feature Niche - Ensuite


Towel Ring - Upstairs Powder Room


Vanity - Downstairs Powder Room


Bath - Main Bathroom

Thursday, 15 November 2012

Good news

Another week down and another week of changes.

This week we have had painters over the weekend, garage door installed, gyprockers and carpenters finishing off things before the painters return to finish off, handles installed to all doors including my beautiful front door.

We spoke with our SS today and he expects handover on the 14th of December.
Everything is booked in up until that date.
Plumbing and Electrical fit off next week, bricklayers coming back next week to fix acid burnt bricks.
Carpet is booked in for the 27th.
Shower screens, mirrors and wardrobes were measured yesterday.

So not long now, I hope it all comes together. Cant wait to spend Christmas in our new home and spend our annual leave working on it.

Lets hope the bank plays nicely this time. The
valuer took 3 weeks last time which delayed our payment.

We are meeting the supervisor on site next week so I'll add more photos then.

Sunday, 11 November 2012

A photo update....

A few exterior photos....
Our beautiful front door - handle to come....
A quick snapshot of the front cladding now painted.
Meter Box

Friday, 9 November 2012

November Update

Time for a November update....

Since my last update, we've had some action.

After paying for lock up 6 weeks ago... we finally have a front door, and it is so beautiful.

The carpenters had to knock out some bricks at the top of the door for it to fit as the bricklayers had bricked it up for a normal door, not  a pivot door.
The front porch ceiling has now been sheeted and the cladding out the front is finished now.

The carpenters have also been through and done the bulkheads in the kitchen/pantry, and redone the bulkhead over the stairs, as it was too low with the lowered ceiling.
We are thankful that our supervisor picked this up, we're both average height and hadn't realised that tall people would hit their heads on the way down.

The gyprockers have been through and fixed up the bulkheads, some areas to the stairs, downstairs powder room & man hole.

The painters started yesterday, doing the first coat of paint on walls and ceilings.
The gyprockers will be back before they do anymore painting to patch imperfections on the walls etc

Our supervisor phoned yesterday to confirm a few paint things.
We are staining the internal sliding door to the laundry and the external laundry door, the external garage door will also be stained, and the front door will be stained too.

The staircase is going to be stained the same as the display home at Kellyville.
I can't wait to see the staircase unveiled and finished off.

So this weeks action plan is paint & gyprock.

With 6 weeks until Christmas, I am starting to doubt we'll be spending Christmas in our new house.
Maybe Santa will bring me a miracle.... I've been good all year, I promise!!

Sunday, 28 October 2012

The start of Week 20!

My last update was filled with a list of jobs that would be done last week.

None of them were done! In fact there were 8 days where the house sat untouched!
That's not good for the stress levels when you have paid for 90% of the house + rent + land repayments.

Finally on Saturday there were tilers there again. They tiled 2 niche in the showers and the bath in the main bathroom. They still need to do the mosaic splashbacks in the bathrooms and grout.

Our supervisor had originally said mid-late November for handover, I doubt that will be the case!
It's frustrating considering our lease expires on the 8th of November.

There is still so much to do, and lots of half jobs done....
Remember the carpenter who was doing the cladding.....the one who started in August.... Well he hasn't finished yet!!
We've been "locked up" for just over a month but there is no sign of our front door, due to a supplier problem and an error in the brickwork to the front of the house which means our door frame won't fit, so bricks need to be knocked out and re-done.

It's disappointing to see other quality builders who started after us with compariable houses (in size and detail) are wizzing past.
We picked this builder based on the speed of build, but it seems that construction time is a lot slower than we were initially anticipating.
Could it be due to the builders undertaking their own turn key developments in neighbour areas?

Fingers crossed things fly this week...



In good news my blog has now hit over 10,000 views! Thank you so much for sharing my journey, I feel very humbled that people take the time to read and contact me to ask further questions.