The bricklayers have been laying bricks all week. The back of the house is completed around the home theatre.
Scaffolding went up yesterday so bricks will continue into next week.
Plumber has been and roughed in all the pipes and gas etc
We had a phone call from our new site supervisor yesterday, introducing himself. We will catch up with him on site soon.
I fell in love with wooden apples in one of our builders display homes and finally asked them where they came from!
So I have made my first purchase for our new home! Quite possibly the most expensive apples I'll ever buy, but they will look fantastic in the kitchen!
Showing posts with label plumbing. Show all posts
Showing posts with label plumbing. Show all posts
Friday, 20 July 2012
More bricks and scaffold..
Labels:
bricks,
kitchen,
plumbing,
scaffold,
site supervisor
Tuesday, 17 July 2012
And then there were bricks!
Monday marked our 5th week since our build started.
Our lovely Boral Blackheath bricks arrived on site last Friday.
Brickies were on site first thing Monday morning and they are progressing well.
The colour in the bricks is lovely.
Monday also saw our plumbing being roughed in and dirt removal.
Our lovely Boral Blackheath bricks arrived on site last Friday.
Brickies were on site first thing Monday morning and they are progressing well.
The colour in the bricks is lovely.
Monday also saw our plumbing being roughed in and dirt removal.
![]() |
| Boral Blackheath Bricks |
![]() |
| Front of House |
![]() |
| Kitchen side of house |
![]() |
| Door - Rear of Garage |
![]() |
| Front of Garage |
Sunday, 8 July 2012
Frames etc
I've been a bit slack with the updates!
It's been moving along quite quickly, since my last update, we've had plumbing & sewer connections done, windows delivered (about 2 weeks early!), frames delivered and started and our site fence erected.
Here are some photos of the story so far....
Currently there are carpenters working on the second floor frames, soon it will resemble a house!!
It's been moving along quite quickly, since my last update, we've had plumbing & sewer connections done, windows delivered (about 2 weeks early!), frames delivered and started and our site fence erected.
Here are some photos of the story so far....
![]() |
| Slab |
![]() |
| Windows - Delivered 2 weeks early! Oops |
![]() |
| Our frames |
![]() |
| First floor started |
![]() |
| The kitchen & butlers pantry |
![]() |
| Alfresco |
![]() |
| The view from the corner of the backyard |
Currently there are carpenters working on the second floor frames, soon it will resemble a house!!
Thursday, 21 June 2012
More progress...
Another busy day on site. Pipes, reo & waffle pods installed....
![]() |
| Front corner |
![]() |
| Front view |
![]() |
| View from the back corner |
Subscribe to: