Sunday, 11 November 2012

A photo update....

A few exterior photos....
Our beautiful front door - handle to come....
A quick snapshot of the front cladding now painted.
Meter Box

Friday, 9 November 2012

November Update

Time for a November update....

Since my last update, we've had some action.

After paying for lock up 6 weeks ago... we finally have a front door, and it is so beautiful.

The carpenters had to knock out some bricks at the top of the door for it to fit as the bricklayers had bricked it up for a normal door, not  a pivot door.
The front porch ceiling has now been sheeted and the cladding out the front is finished now.

The carpenters have also been through and done the bulkheads in the kitchen/pantry, and redone the bulkhead over the stairs, as it was too low with the lowered ceiling.
We are thankful that our supervisor picked this up, we're both average height and hadn't realised that tall people would hit their heads on the way down.

The gyprockers have been through and fixed up the bulkheads, some areas to the stairs, downstairs powder room & man hole.

The painters started yesterday, doing the first coat of paint on walls and ceilings.
The gyprockers will be back before they do anymore painting to patch imperfections on the walls etc

Our supervisor phoned yesterday to confirm a few paint things.
We are staining the internal sliding door to the laundry and the external laundry door, the external garage door will also be stained, and the front door will be stained too.

The staircase is going to be stained the same as the display home at Kellyville.
I can't wait to see the staircase unveiled and finished off.

So this weeks action plan is paint & gyprock.

With 6 weeks until Christmas, I am starting to doubt we'll be spending Christmas in our new house.
Maybe Santa will bring me a miracle.... I've been good all year, I promise!!

Monday, 17 September 2012

Mid September Update

Things are progressing well so far this month.

We've had the rear roof installed, metal roof over garage and front porch installed, bathroom waterproofed, air conditioning roughed in, electrical roughed in, bricks washed, insulation installed, and today the gyprock arrived for a start tomorrow.
Our SS is sticking to the scheduled dates he gave us a few weeks back.

I'd like to tick the box that says cladding complete, but oh my gosh, we have the worlds slowest carpenter working on our place.
Not sure what his story is, but he started back on the 21st of August!
He has slowly been cladding the front.... it's almost complete, it just needs the trims to be done.

Then there is the easylap boards at the back, he's done part of the (rear) side of the house, but the back of the house is still to be done....
It would have been nice to have made the house watertight before the insulation went in.
The back of the house is still exposed, I'm just hoping the rain we've had this afternoon hasn't ruined the insulation.

No doubt the gyprockers will be waiting for him to do our lowered bulk heads in the kitchen and entrance.
Then there are the eaves at the back to be done too.

He is so frustrating!!



Saturday, 1 September 2012

Could it be a speedy September?

What an end to a slow August!

Friday saw the scaffolding being removed, the timber frames for the front porch installed and the roof rails put up on the back roof.

Next week our back roof should go on, as well as the garage roof and porch roof. Once this is done the cladding will be finished off.

Lock up is drawing closer but no real time frame.

The golf clubhouse opened yesterday, we went for lunch there today.
We parked out the front of our house and walked the 250m to the clubhouse.

Here are some photos of our house with the scaffold down.

Wednesday, 29 August 2012

End of August update

There isn't much to update, August has been a slow month.
Next Monday marks our 12th week since we started.

Bricks finally got cleaned, part of the cladding has been installed and painted, downpipes have been installed to the upper level of the house.
It looks as though the roof at the back of the house and the garage must go on next before the rest of the cladding can be put on. I think the roofing for the front porch and garage has to be delivered first.

We are happy with the paint colour we picked for the cladding, it was one thing we weren't certain about, and it looks fantastic.

The SS says we should be at lock up in about 3 weeks.
Hopefully September can be dubbed Speedy September... there are homes in the builders nearby estate that started 4 weeks after us, that are at the same stage as ours.

I haven't taken decent photos lately, so here are a few dodgey ones (couldn't find the camera cord!)

Back of the house

Front of house


Friday, 17 August 2012

Quick update & a nearmap view

Gutter, fascia and roof tiles were completed at the start of the month.

Eaves were installed earlier this week.

I have been a bit slack and haven't taken a photo of our roof tiles, it's hard to take a good photo with the scaffold still up.

Bricks are to be cleaned next then comes the cladding, so once the scaffold is down, I'll be able to take a photo.

In the meantime, nearmap.com has updated their photos, so here is the timeline from September 2011/May 2012 and the most recent being 2nd of August 2012.



Satellite View - Our house outlined in red

The golf course and clubhouse open at the end of the month. Looking forward to sharing some good times there in the future.

Friday, 25 November 2011

An update....

With our house sold, a 30 day settlement and the mad hunt for a rental, the last thing I've had time for is to update my blog.

So whilst I procrastinate packing the last of our possessions to make the move over this weekend and Monday, I thought an update was in order!

We've approved our 2nd set of plans to now go to the SCR committee, and then onto DA approval with council.
Work is progressing in our street, it's still fenced off, so we can't get up there, but each week we drive up to the gates and peer over. There is asphalt being laid, pipes being placed in the ground and machinery buzzing around up there.

The golf course clubhouse is progressing well, and we're hearing that it will open in April next year.
We're looking forward to being able to walk 250m down the road to the clubhouse for dinner or lunch in the future.

We believe that our land will settle in February/March 2012, so we've got some time to save some money and work through our internal colour selections and tile selections.

Now for our exterior colour selections:

Bricks - BORAL - Blackheath
Mortar - Off white/Raked


Tiles - Monier Elabana profile in Barramundi
Guttering - Ironstone
Fascia - Paperbark

















Downpipe/Rainwater Tank - Ironstone

Windows/Flyscreens - Paperbark

Cladding - Taubmans Coffee Break










Garage Door - B&D Panelmasta Contemporary - Merino (Paperbark)

Front door - Corinthian Doors - Pivot door











 So I guess I had best be off, more boxes to pack!!

Until next time....