There is 5 days until our apparent handover date.
Our PCI walk through was pushed back from last Wednesday afternoon to tomorrow afternoon.
The list I posted last week still has a lot outstanding which concerns me.
The things that got completed from the list were insulation was spread in the roof, the tiler completed the tiling upstairs, but still needs to return to finish the splashback and the inside was cleaned up a bit.
Which leaves 5 days for the following things to be done.... as well as a few defects we've picked up along the way.
- shower screens, wardrobe railings, shelving
in pantry, mirrors
- fly screens and screen doors
- acid burnt bricks need replacing & a few bricks need
fixing.
- inspection point needs to be bricked up
- timber screen to the front facade needs to be installed (enter worlds slowest carpenter again!)
- paint
touch ups
- carpet
- tiling - kitchen splashback
-
stair case needs to be stained
- site clean up
- internal clean (final clean)
Carpet is meant to be tomorrow, staircase was meant to be painted on Saturday, which didn't happen.
Our SS queried our stain colour, which has made me nervous. We had chosen Ebony as per the display home, but our SS said it's very dark, so a few frantic phone calls to the lovely interior ladies and I am hoping it turns out okay.
We NEED to handover on Friday as we have to hand back our rental keys on the Tuesday afternoon.
In other news, one of our lounges has been delivered, it is still in boxes, can't wait to open it!!
Our rental resembles a warehouse with boxes everywhere. The clutter is making me twitchy.
The DA for the retaining wall was approved last week. So will be ready to start that as soon as we're in.
Good news, the bank valuation has come through and I can pick up the final cheque on Friday morning, I am so glad that is all sorted, I was petrified that the bank would delay things.
Fingers crossed everything falls into place this week, I can't wait to move into my beautiful new home, and unpack all our belongings that have been boxed up for over a year now.
Better keep packing, there is still a bit to box up & a whole lot of cleaning to do!
Showing posts with label carpet. Show all posts
Showing posts with label carpet. Show all posts
Saturday, 8 December 2012
Not long to go now
Labels:
carpet,
facade,
mirrors,
moving house,
paint,
PCI,
shower screen,
splashback,
staircase,
tiling
Thursday, 15 November 2012
Good news
Another week down and another week of changes.
This week we have had painters over the weekend, garage door installed, gyprockers and carpenters finishing off things before the painters return to finish off, handles installed to all doors including my beautiful front door.
We spoke with our SS today and he expects handover on the 14th of December.
Everything is booked in up until that date.
Plumbing and Electrical fit off next week, bricklayers coming back next week to fix acid burnt bricks.
Carpet is booked in for the 27th.
Shower screens, mirrors and wardrobes were measured yesterday.
So not long now, I hope it all comes together. Cant wait to spend Christmas in our new home and spend our annual leave working on it.
Lets hope the bank plays nicely this time. The
valuer took 3 weeks last time which delayed our payment.
We are meeting the supervisor on site next week so I'll add more photos then.
This week we have had painters over the weekend, garage door installed, gyprockers and carpenters finishing off things before the painters return to finish off, handles installed to all doors including my beautiful front door.
We spoke with our SS today and he expects handover on the 14th of December.
Everything is booked in up until that date.
Plumbing and Electrical fit off next week, bricklayers coming back next week to fix acid burnt bricks.
Carpet is booked in for the 27th.
Shower screens, mirrors and wardrobes were measured yesterday.
So not long now, I hope it all comes together. Cant wait to spend Christmas in our new home and spend our annual leave working on it.
Lets hope the bank plays nicely this time. The
valuer took 3 weeks last time which delayed our payment.
We are meeting the supervisor on site next week so I'll add more photos then.
Wednesday, 1 August 2012
Tile Consultation
Our tiles have been chosen!
Our builder prefers to do tile selections once the bricks are started, this ensures all tiles are available and not discontinued or out of stock when it comes to laying them.
We definitely weren't as prepared for the tile consultation as we were the colour consultation, and it proved difficult to do homework, as it's hard to know by looking at magazines and display homes what things are really worth!
Our consultant was extremely helpful, and reassured us about colours
We also had an idea of what we thought we would spend, but once we were there and the creativity started flowing, it wasn't long until we were over the "budget"... oops!
Downstairs Powder Room -Floor - Mocha Matt 450 x 450 to floor - straight lay
Concealed Floor Waste
Splashback - Feature tile between vanity and mirror including return
(Vanity - Mushroom Linea. Caesarstone - Osprey)

Kitchen -Floor - Mocha Matt 450 x 450
Splashback - 300 x 600 Horizontal Lay (including Butlers Pantry)
Mosaic lay 2 rows wide vertical in line with cooktop finishes (Excluding Butlers Pantry)
(Lower cupboards - Nocturne Oak. Feature Cupboards - Stipple Hemp. Caesarstone - Almond Rocca)

Laundry -
Floor - Mocha Matt 450 x 450
Square Floor waste
Skirting - Mocha Matt 1/2 tile
Splashback - 300 x 100 lay stack bond

Upstairs Powder Room/Main Bathroom -Floor - Mocha Matt 300 x 300
Square Floor waste
Walls - Snow White 300 x 600 - Horizontal Lay
Splashback - Feature tile between vanity and mirror
Shower Niche - Splashback tile repeated in niche
(Vanity - Mushroom Linea. Caesarstone - Osprey)

Our builder prefers to do tile selections once the bricks are started, this ensures all tiles are available and not discontinued or out of stock when it comes to laying them.
We definitely weren't as prepared for the tile consultation as we were the colour consultation, and it proved difficult to do homework, as it's hard to know by looking at magazines and display homes what things are really worth!
Our consultant was extremely helpful, and reassured us about colours
We also had an idea of what we thought we would spend, but once we were there and the creativity started flowing, it wasn't long until we were over the "budget"... oops!
Downstairs Powder Room -Floor - Mocha Matt 450 x 450 to floor - straight lay
Concealed Floor Waste
Splashback - Feature tile between vanity and mirror including return
(Vanity - Mushroom Linea. Caesarstone - Osprey)

Kitchen -Floor - Mocha Matt 450 x 450
Splashback - 300 x 600 Horizontal Lay (including Butlers Pantry)
Mosaic lay 2 rows wide vertical in line with cooktop finishes (Excluding Butlers Pantry)
(Lower cupboards - Nocturne Oak. Feature Cupboards - Stipple Hemp. Caesarstone - Almond Rocca)

Laundry -
Floor - Mocha Matt 450 x 450
Square Floor waste
Skirting - Mocha Matt 1/2 tile
Splashback - 300 x 100 lay stack bond

Upstairs Powder Room/Main Bathroom -Floor - Mocha Matt 300 x 300
Square Floor waste
Walls - Snow White 300 x 600 - Horizontal Lay
Splashback - Feature tile between vanity and mirror
Shower Niche - Splashback tile repeated in niche
(Vanity - Mushroom Linea. Caesarstone - Osprey)

Ensuite - Floor - Charcoal Satin 300 x 300
Concealed Floor Waste
Feature wall behind Freestanding Bath - 440 x 890 Lay Horizontal
Walls (including splashback) Snow White - 300 x 600 Lay Horizontal
Shower Niche - Mosaic
(Vanity - Mushroom Linea. Caesarstone - Osprey)
Concealed Floor Waste
Feature wall behind Freestanding Bath - 440 x 890 Lay Horizontal
Walls (including splashback) Snow White - 300 x 600 Lay Horizontal
Shower Niche - Mosaic
(Vanity - Mushroom Linea. Caesarstone - Osprey)

Labels:
bathroom,
carpet,
ensuite,
feature wall,
freestanding bath,
kitchen,
laundry,
splashback,
tile selection,
tiles
Wednesday, 22 February 2012
Colours....
Yesterday we met with our builders fantastic Colour Consultant and we did our interior colours, as well as any changes we wanted to make.
I can honestly say that the preparation and research we did before the appointment paid off.
It was quite straight forward, there were no arguments, temper tantrums or tears.... all in all, it was quite a stress free experience!
So without further ado... Here are our selections:
Walls - Taubmans "Martini"
Ceiling - Ceiling White
Door Frames - Taubmans "China White"
Feature Wall - Taubmans "Stone Drab"
Carpet Colour - "Donkey" Wool Blend carpet
Door Furniture -
External doors - Gainsborough - Amelia Lever handle & 851 deadlock in Satin Chrome
Internal Doors - Gainsborough - Amelia Lever handle in Satin Chrome
Wardrobe Doors - Sterling 300 Square Handles
Kitchen Colours -
Caesarstone - Almond Rocca (Bench tops & Waterfall Edge)
Cupboard Doors - Laminex - Nocturne Oak - Natural Finish
Feature Cupboards (Overhead cupboards) - Laminex - Stipple Hemp - Natural Finish
Tapware - Kitchen -
Irwell pin lever hob "rectangular" spout with water purifier
Handles to lower doors of kitchen, no handles on upper cupboards.
Bathrooms -
Caesarstone - Osprey
Cupboards - Laminex - Mushroom Linea
Doors - Press Open doors
A few changes we've made to our plan so far:
- Change bathroom towel rails from single to double
- Upgrade carpet underlay
- Upgrade staircase (see the staircase in the Feature Wall photo above)
- Pivot Door to front door with "Omni" handle
- Rainforest showerhead to ensuite
- Ducted Air Conditioning
- Fit-out to pantry
- Change laundry door to a cavity slider
- Include broom section to laundry cupboard
- Tiling to lower level living spaces
- Increase ceiling height to lower level
- Lowered feature ceiling to entry hallway & kitchen
In the coming weeks we'll have our Electrical appointment, to place power points and lighting.
Our tile selection appointment isn't until just prior to lock up stage, so we've got a few months to think about what we'd like to do, I think we've got a vague idea though.
It's great to be finally making progress, its going to be a slow process, but worth it in the end!!
I can honestly say that the preparation and research we did before the appointment paid off.
It was quite straight forward, there were no arguments, temper tantrums or tears.... all in all, it was quite a stress free experience!
So without further ado... Here are our selections:
Walls - Taubmans "Martini"
Ceiling - Ceiling White
Door Frames - Taubmans "China White"
Feature Wall - Taubmans "Stone Drab"
Carpet Colour - "Donkey" Wool Blend carpet
Door Furniture -
External doors - Gainsborough - Amelia Lever handle & 851 deadlock in Satin Chrome
Internal Doors - Gainsborough - Amelia Lever handle in Satin Chrome
Wardrobe Doors - Sterling 300 Square Handles
| Wall Colour, Feature Wall Colour & Carpet Colour |
| Feature Wall location (Wall with the doorway) |
Caesarstone - Almond Rocca (Bench tops & Waterfall Edge)
Cupboard Doors - Laminex - Nocturne Oak - Natural Finish
Feature Cupboards (Overhead cupboards) - Laminex - Stipple Hemp - Natural Finish
| Kitchen Colours |
Kitchen Appliances -
![]() |
| 900mm Dual Fuel Cooker |
![]() | ||
| Rangehood |
Tapware - Kitchen -
Irwell pin lever hob "rectangular" spout with water purifier
Handles to lower doors of kitchen, no handles on upper cupboards.
Bathrooms -
Caesarstone - Osprey
Cupboards - Laminex - Mushroom Linea
Doors - Press Open doors
| Bathroom Colours |
![]() |
| Drawer Handles |
| Decina "Cool" Freestanding Bath to Ensuite |
A few changes we've made to our plan so far:
- Change bathroom towel rails from single to double
- Upgrade carpet underlay
- Upgrade staircase (see the staircase in the Feature Wall photo above)
- Pivot Door to front door with "Omni" handle
- Rainforest showerhead to ensuite
- Ducted Air Conditioning
- Fit-out to pantry
- Change laundry door to a cavity slider
- Include broom section to laundry cupboard
- Tiling to lower level living spaces
- Increase ceiling height to lower level
- Lowered feature ceiling to entry hallway & kitchen
In the coming weeks we'll have our Electrical appointment, to place power points and lighting.
Our tile selection appointment isn't until just prior to lock up stage, so we've got a few months to think about what we'd like to do, I think we've got a vague idea though.
It's great to be finally making progress, its going to be a slow process, but worth it in the end!!
Labels:
appliances,
bathroom,
caesarstone,
carpet,
colour consultation,
colour selection,
cupboards,
doors,
feature wall,
freestanding bath,
handles,
kitchen,
paint,
tapware,
upgrades