Things are progressing well so far this month.
We've had the rear roof installed, metal roof over garage and front porch installed, bathroom waterproofed, air conditioning roughed in, electrical roughed in, bricks washed, insulation installed, and today the gyprock arrived for a start tomorrow.
Our SS is sticking to the scheduled dates he gave us a few weeks back.
I'd like to tick the box that says cladding complete, but oh my gosh, we have the worlds slowest carpenter working on our place.
Not sure what his story is, but he started back on the 21st of August!
He has slowly been cladding the front.... it's almost complete, it just needs the trims to be done.
Then there is the easylap boards at the back, he's done part of the (rear) side of the house, but the back of the house is still to be done....
It would have been nice to have made the house watertight before the insulation went in.
The back of the house is still exposed, I'm just hoping the rain we've had this afternoon hasn't ruined the insulation.
No doubt the gyprockers will be waiting for him to do our lowered bulk heads in the kitchen and entrance.
Then there are the eaves at the back to be done too.
He is so frustrating!!
Showing posts with label roof. Show all posts
Showing posts with label roof. Show all posts
Monday, 17 September 2012
Mid September Update
Labels:
bricks,
carpenter,
cladding,
gyprock,
insulation,
rain,
roof,
rough in,
Waterproof
Saturday, 8 September 2012
Picking up pace...
This week progressed well!
Rear lower roof went on Monday, our missing gutter also went on too.
Thursday saw the installation of the metal roof to the garage and front porch including trims and box gutters .
Friday, the cavity sliding door to the laundry was installed to enable the wet areas to be waterproofed.
The waterproofer will return once the walls are gyprocked to complete the work.
Our SS gave us a few key dates to look forward to.
The main ones should see gyprock on the 17th September, fix out on the 24th September and the most exciting one, kitchen on the 28th September!!!
Here are some new photos (with all the wind our fence blew over)
Rear lower roof went on Monday, our missing gutter also went on too.
Thursday saw the installation of the metal roof to the garage and front porch including trims and box gutters .
Friday, the cavity sliding door to the laundry was installed to enable the wet areas to be waterproofed.
The waterproofer will return once the walls are gyprocked to complete the work.
Our SS gave us a few key dates to look forward to.
The main ones should see gyprock on the 17th September, fix out on the 24th September and the most exciting one, kitchen on the 28th September!!!
Here are some new photos (with all the wind our fence blew over)
Saturday, 1 September 2012
Could it be a speedy September?
What an end to a slow August!
Friday saw the scaffolding being removed, the timber frames for the front porch installed and the roof rails put up on the back roof.
Next week our back roof should go on, as well as the garage roof and porch roof. Once this is done the cladding will be finished off.
Lock up is drawing closer but no real time frame.
The golf clubhouse opened yesterday, we went for lunch there today.
We parked out the front of our house and walked the 250m to the clubhouse.
Here are some photos of our house with the scaffold down.
Friday saw the scaffolding being removed, the timber frames for the front porch installed and the roof rails put up on the back roof.
Next week our back roof should go on, as well as the garage roof and porch roof. Once this is done the cladding will be finished off.
Lock up is drawing closer but no real time frame.
The golf clubhouse opened yesterday, we went for lunch there today.
We parked out the front of our house and walked the 250m to the clubhouse.
Here are some photos of our house with the scaffold down.
Wednesday, 29 August 2012
End of August update
There isn't much to update, August has been a slow month.
Next Monday marks our 12th week since we started.
Bricks finally got cleaned, part of the cladding has been installed and painted, downpipes have been installed to the upper level of the house.
It looks as though the roof at the back of the house and the garage must go on next before the rest of the cladding can be put on. I think the roofing for the front porch and garage has to be delivered first.
We are happy with the paint colour we picked for the cladding, it was one thing we weren't certain about, and it looks fantastic.
The SS says we should be at lock up in about 3 weeks.
Hopefully September can be dubbed Speedy September... there are homes in the builders nearby estate that started 4 weeks after us, that are at the same stage as ours.
I haven't taken decent photos lately, so here are a few dodgey ones (couldn't find the camera cord!)
Next Monday marks our 12th week since we started.
Bricks finally got cleaned, part of the cladding has been installed and painted, downpipes have been installed to the upper level of the house.
It looks as though the roof at the back of the house and the garage must go on next before the rest of the cladding can be put on. I think the roofing for the front porch and garage has to be delivered first.
We are happy with the paint colour we picked for the cladding, it was one thing we weren't certain about, and it looks fantastic.
The SS says we should be at lock up in about 3 weeks.
Hopefully September can be dubbed Speedy September... there are homes in the builders nearby estate that started 4 weeks after us, that are at the same stage as ours.
I haven't taken decent photos lately, so here are a few dodgey ones (couldn't find the camera cord!)
![]() |
| Back of the house |
![]() |
| Front of house |
Friday, 17 August 2012
Quick update & a nearmap view
Gutter, fascia and roof tiles were completed at the start of the month.
Eaves were installed earlier this week.
I have been a bit slack and haven't taken a photo of our roof tiles, it's hard to take a good photo with the scaffold still up.
Bricks are to be cleaned next then comes the cladding, so once the scaffold is down, I'll be able to take a photo.
In the meantime, nearmap.com has updated their photos, so here is the timeline from September 2011/May 2012 and the most recent being 2nd of August 2012.
The golf course and clubhouse open at the end of the month. Looking forward to sharing some good times there in the future.
Eaves were installed earlier this week.
I have been a bit slack and haven't taken a photo of our roof tiles, it's hard to take a good photo with the scaffold still up.
Bricks are to be cleaned next then comes the cladding, so once the scaffold is down, I'll be able to take a photo.
In the meantime, nearmap.com has updated their photos, so here is the timeline from September 2011/May 2012 and the most recent being 2nd of August 2012.
![]() |
| Satellite View - Our house outlined in red |
The golf course and clubhouse open at the end of the month. Looking forward to sharing some good times there in the future.
Wednesday, 11 July 2012
Second floor & Roof
We're 3.5 weeks into our build and our frame is up, our site has been tidied up and now we're waiting for the bricks to be delivered (and the invoice for our frame progress payment...)
An brief instagram photo update....
Until next time....
An brief instagram photo update....
| First floor |
| Second floor |
| Roof truss & windows |
Until next time....
Subscribe to:
Posts (Atom)