Things are progressing well so far this month.
We've had the rear roof installed, metal roof over garage and front porch installed, bathroom waterproofed, air conditioning roughed in, electrical roughed in, bricks washed, insulation installed, and today the gyprock arrived for a start tomorrow.
Our SS is sticking to the scheduled dates he gave us a few weeks back.
I'd like to tick the box that says cladding complete, but oh my gosh, we have the worlds slowest carpenter working on our place.
Not sure what his story is, but he started back on the 21st of August!
He has slowly been cladding the front.... it's almost complete, it just needs the trims to be done.
Then there is the easylap boards at the back, he's done part of the (rear) side of the house, but the back of the house is still to be done....
It would have been nice to have made the house watertight before the insulation went in.
The back of the house is still exposed, I'm just hoping the rain we've had this afternoon hasn't ruined the insulation.
No doubt the gyprockers will be waiting for him to do our lowered bulk heads in the kitchen and entrance.
Then there are the eaves at the back to be done too.
He is so frustrating!!