Thursday, 29 November 2012

Countdown is on!

2 weeks until handover...

Assuming all goes to plan.

I am quietly confident that everything will come together nicely, but I don't want to get my hopes up too high.

We have handed in our notice to our real estate agent, paid for our insurance and we received our final progress payment yesterday and that has been sent off to the bank.
Let's hope the bank gets its act together and processes it quickly and doesn't delay anything.

We had a sticky beak in the window yesterday, the tiler has been there tiling the main living area floor downstairs. It looks fantastic.

We have a walk through booked in for next Wednesday, so hopefully all the little things that need doing will be done or close to being done.

A few things left to do still;
- shower screens, wardrobe railings, shelving in pantry, mirrors
- fly screens and screen doors
- insulation in the roof requires spreading
- acid burnt bricks need replacing & a few bricks need fixing.
- timber screen to the front facade needs to be installed
- paint touch ups
- carpet
- tiling - a couple of tiles need to be done
- stair case needs to be stained
- site clean up
- internal clean

And then the obvious ones, all the installation of appliances etc on handover.

We are taking delivery of one of our lounges next Wednesday, not sure where we'll store that, but King couldn't deliver it once we were in because their warehouse is under renovation.

The DA for retaining walls should be through soon, we had to submit additional paperwork, so now we just wait!
That's our Christmas job, installed 900mm high retaining walls to the rear of our block and to the sides.



1 comment: